Report on
Conservation works undertaken on the Dovecote, Bruton.
November 2010.
Contractor: Renˇ Rice.
Client: The National Trust.
1.
Introduction.
The history and
general description of the building are more than adequately covered in the
archeologistÕs report so they will not be entered into here except where
necessary to provide background information about conservation choices made
during the project. The most salient point is that the four sided tower, once
roofed now has no roof leaving exposed wall tops on the four gables, three of
which remain.
The second most
salient point in relationship to choices of scope and method of the works
relates to budget. A full top to bottom, interior and exterior conservation
project was not possible and budgetary restrictions limited the work to the top
third of the tower with special emphasis on cappings and the stitching of
cracks/bulges.
Pre-contract
photographs can be found in the pre-contract photographic survey folder on the
disc.
2. Scope of the
Works.
2.1.
Gable crosses
2.1.1
West gable
All hollow joints
were filled- methods and mixes dependent on scale of fissure. Areas of the
concrete capping beneath the gable cross were cut out and replaced.
2.1.2. South gable
All hollow joints
were filled- methods and mixes dependent on scale of fissure. Areas of the
concrete capping beneath the gable cross were cut out and replaced.
2.1.3 East gable
All hollow joints
were filled- methods and mixes dependent on scale of fissure. Areas of the
concrete capping beneath the gable cross were cut out and replaced.
2.2. Cappings: concrete
2.2.1. Cutting out and replacing loose concrete
capping.
North
(truncated)gable
East gable
Junction of north and west gables
south west
corner
2.2.2. Drilling
through capping and grouting wall
top.
After pointing up
localized walls to avoid grout runoff 25mm holes were drilled through the
concrete capping and grout composed of nhl 3.5 hydraulic lime and sharp sand
with water was introduced via
funnel into the holes. In total some 15 buckets of grout were poured
into the wall tops.
2.3. Vegetation
removal and subsequent masonry rebuilding.
All woody growth
was removed from the building and areas were dismantled where necessary to
chase out roots, esp in the north west corner.
2.3.1.a
North west corner
Subsequent to the
last picture above the Elder root
to the bottom left was cut out and minor roots drawn from the interior of the
masonry. All stones had been stored in order and were rebuilt in reverse order.
The exterior
facework of the north (truncated) gable was poorly bonded to the core so 8mm
stainless threaded bar was inserted and resined into joints as the internal
masonry build progressed. In all 3no bars were fixed as the build progressed.
Rebuild:
Subsequent to the
rebuild of the masonry and the repositioning of the original reclaimed stone roofing the area was recapped with
concrete to match the existing. (see photograph above)
2.4. Works to
masonry surfaces
2.4.1. Grouting small cracks with syringe and
clay birdsnests using St Astier Coulinex grout. (Coulinex product information
sheet on disc.)
Mix: Approx 1
Coulinex to 0.8 part water.
It was not always
easy to introduce grout into the smallest of the cracks but where possible a
catheter syringe was used with a clay seal. Where gravity feed was possible,
clay birds nests attached to the masonry were filled with liquid grout which
was encouraged to flow into the pre-wetted crack.
2.4.2. Grouting larger cracks using grouting gun and soft sand with nhl 3.5
For the larger
cracks of 4mm and above a grout gun was used with a 5mm nozzle using a mixture
of soft sand and St. Astier nhl 3.5 hydraulic lime. This
was mixed to a gunnable consistency with water mechanically in a clean bucket.
At the highest
levels, most exposed, the nhl 3.5 was substituted with nhl 5.
2.4.3. Pointing and joint filling using coarse
hydraulic lime mortar mix
Larger open joints
and other lacunae were filled with coarse lime mortar in normal pointing style.
Mix: 1 part nhl 3.5: 2 parts Chardstock sand: 1. Part Bath Stone Dust washed: 0.25 part crushed coal
(this started out as 2 parts Bideford grit: 1 part Portland Dust: 0.25 parts crushed coal but this was too grey and too coarse)
At the
highest levels, most exposed, the nhl 3.5 was substituted with nhl 5.
2.5. Insertion
of Cintec ties.
Six ties were inserted in the eastern
corner of the south wall where there was a pronounced bulge in the masonry
(See Mann Williams report)
2.5.1. South
Wall east corner
North wall west corner
2.5.2. A further two ties some 2m in length were
inserted into the north wall at itÕs abutment with the west wall to tie the two
walls across a vertical crack ( see Mann Williams report)
The works extended
from the apex of the gables to a point some 6 metres below both interior and
exterior.